SCU battery management and hybrid inverter systems
| Device Type | Variants | Modbus TCP (Ethernet) | RS485 | Curtailment |
|---|
| BRESS 150/240 | | ✅ | ❌ | ✅ |
| Battery container |
|
In the SCU interface:
- Go to "Maintenance"
- Go to "Comm Settings"
- Go to "PCS"
- Under "BMS: Number of devices" -> Set this to the amount of batteries / BMS systems that are connected.
GRES uses the same SCU interface path, but configure based on battery rooms (up to 4 groups):
- Go to "Maintenance" → "Comm Settings" → "PCS"
- Set "BMS: Number of devices" to your battery room count (1-4 for GRES-300-200)
- Ensure PCS remote control is enabled for curtailment
- Modbus address: Default
1 (matches driver DEFAULT_BUS_ADDRESS: 1)
Last updated August 24, 2026