In beta and available on request. The additions in this overview require the matching integration or controller update and are not confirmed as part of the standard customer release. Request them through your existing Eniris support conversation. The status applies to these additions, not to every existing function of the devices listed elsewhere on this page.
| Model / system | Beta addition | Validation and conditions |
|---|---|---|
| UE-29.9K-T4-HA1 | RS485 monitoring and prepared battery control | High-power mapping; exact variant requires physical commissioning |
| UE-30K-T4-HA1 | RS485 monitoring and prepared battery control | High-power mapping; exact variant requires physical commissioning |
| UE-40K-T4-HA1 | RS485 monitoring and prepared battery control | High-power mapping; exact variant requires physical commissioning |
| UE-50K-T4-HA1 | RS485 monitoring and prepared battery control | High-power mapping; exact variant requires physical commissioning |
| UE-60K-T4-HA1 | RS485 monitoring and prepared battery control | Hardware readings checked on 60 kW; full control commissioning required |
| Model / system | Beta addition | Validation and conditions |
|---|---|---|
| UE-8K-T2-HA1 | Separate T2 monitoring/control mapping | Command scale depends on protocol; physical commissioning required |
| UE-10K-T2-HA1 | Separate T2 monitoring/control mapping | Command scale depends on protocol; physical commissioning required |
| UE-12K-T2-HA1 | Separate T2 monitoring/control mapping | Measurements checked; V2.00 command scale 0.1 kW; control test pending |
| Model / system | Beta addition | Validation and conditions |
|---|---|---|
| UE-3.68K-S2-LA1 | Single-phase battery/PV mapping and prepared control | Match firmware/interface; full physical validation not established |
| UE-5K-S2-LA1 / RESS-1P-5K-L02 | Single-phase battery/PV mapping and prepared control | Match firmware/interface; full physical validation not established |
See integration details for connection requirements and operating limitations.
A custom RS485 integration is available for UE-29.9K/30K/40K/50K/60K-T4-HA1, with measurement and battery-power control. A 60 kW unit has been read on hardware; this does not validate every listed power variant. Use the high-power protocol scaling and the actual installed battery limits.
UE-8K/10K/12K-T2-HA1 uses a different protocol mapping. V1.20A monitoring uses 0.01 kW measurement steps, while the command step depends on the reported protocol version. A 12 kW unit reporting V2.00 uses 0.1 kW command steps. Measurements have been checked; the prepared control changes still require physical commissioning. Do not reuse the 60 kW scaling.
Custom variants exist for UE-3.68K-S2-LA1 and UE-5K-S2-LA1 / RESS-1P-5K-L02. These use a different single-phase map and include battery/PV monitoring and prepared control. The current firmware and interface must be matched during commissioning; full physical validation is not established for every variant.
These protocols do not provide a confirmed communication watchdog for the implemented control path. The final command can remain active until explicitly released.